HOW IT WORKS

How Optima builds pools in just 6 weeks.

Every Optima build follows the same six steps in the same order. That's how the timeline holds, and it's why the price doesn't move once it's set.

WEEK 01
Excavation

The first move — the pool footprint becomes real.

We dig the pool footprint to spec — 5' standard depth, single continuous phase. The pre-engineered package size means no design phase, no surveys mid-dig, no permit holdups. Crew breaks ground and the excavation is done in days, not weeks.

WHAT YOU SEE THIS WEEK

Your yard going from grass to a precise rectangular pit at the exact dimensions on your contract.

Excavation diagram
WEEK 02
Plumbing, Rebar & Electrical

This is the week the pool's bones are built.

Plumbing lines go in first, the steel cage follows, and electrical finishes it off — all set in place before any concrete is poured.

WHAT YOU SEE THIS WEEK

A steel grid filling the excavated footprint, plumbing lines visible, equipment locations staked out.

Steel and plumbing diagram
WEEK 03
Shotcrete Shell

A critical week — the structure is set this week.

4500 PSI shotcrete is pumped under pressure to form the watertight pool shell. After application, the shell needs a curing period to reach full strength. Everything that follows builds on this.

WHAT YOU SEE THIS WEEK

The shell sprayed, smoothed, and beginning to cure. The pool now has form.

Shotcrete shell diagram
WEEK 04
Tile & Coping

The detail that defines every Optima pool.

Once the shell has cured, the masonry team installs the mitered edge tile coping by hand. This is what creates the seamless waterfall edge — a detail you won't find on standard plaster-and-concrete builds.

WHAT YOU SEE THIS WEEK

The pool's edge transforming from raw shotcrete into a finished tile line.

Tile and coping diagram
WEEK 05
Interior Finish

The surface you'll feel underfoot for 15+ years.

The upgraded quartz or pebble interior finish is applied. We use a higher-grade interior than the plaster most budget builds default to, because plaster fails inside a decade and pebble doesn't. Equipment is commissioned and tested this week.

WHAT YOU SEE THIS WEEK

The interior color of your pool revealed, equipment online, automation panel installed.

Interior finish diagram
WEEK 06
Fill & Start-Up

By the end of the week, the pool is yours.

The pool is filled, the system is started, the water is balanced, and the filter is cleaned. We walk you through the operation of your equipment and automation panel so you're confident running the pool day-to-day.

WHAT YOU SEE THIS WEEK

A full, swimmable pool. The yard is yours again.

Fill and start-up diagram
WHY IT HOLDS

Why the six-week timeline holds.

Most concrete pools take three to six months. Six weeks isn't a sales line — it's a function of how the product is built.

— 01

No custom design phase.

Every Optima pool is one of four preset Optima sizes with a fixed inclusion list. No design studio meetings, no revisions, no waiting on drawings. Permits start the day you reserve.

— 02

No trades to coordinate.

Optima builds the pool. We don't install decking, landscaping, or hardscape. There's no waiting on a sub-contractor, no missed handoffs, and no week-three surprise that pushes the finish into month four.

— 03

The same proven build sequence.

Desert Springs has run this exact six-step build thousands of times. The crew knows what week three looks like before week one starts. That repeatability is what makes the timeline possible.

Desert Springs Pools team
FOX 5 VIEWERS CHOICE GOLD WINNER
PEBBLETECH CERTIFIED INSTALLER
BACKED BY DESERT SPRINGS POOLS AND SPAS

Built by the same team installing luxury pools in Vegas for the last 30 years.

Every Optima pool is built by Desert Springs Pools & Spas. The same team that has installed luxury pools across the Las Vegas Valley for the past three decades. The reason we can offer fixed pricing and financing details and a six-week timeline isn't that we cut corners — it's because we've already done it 11,000 times.

30+ YEARS
In the Las Vegas Valley.
Fox 5 Viewers Choice Gold winner. PebbleTech-certified installer.
11,000+ POOLS
Built across the valley.
One of the largest install volumes of any builder in the Vegas market.
100% IN-HOUSE
Crews, not subs.
Excavation, plumbing, plaster, and equipment all installed by employees, not subs.
RESERVE YOUR BUILD SLOT

Six weeks from now,
you could be swimming.

Pick a package, reserve your build slot with a refundable deposit, and the six-week clock starts. Same crew, same sequence, every build.

PEBBLETECH
CERTIFIED INSTALLER
EXPERIENCE
30+ YEARS
POOLS DELIVERED
11,000+
BUILD YOUR POOL